PROPOSED 2023 Pikes Peak Regional Building Code (PPRBC)
PPRBD will be adopting the 2023 Pikes Peak Regional Building Code (PPRBC). The 2023 PPRBC will adopt by reference the 2021 ICC codes listed below. The Regional Building Department welcomes your input by public comment on the proposed draft amendments. Please use the link below to comment on the proposed draft amendments and/or submit your own amendments for review. Upon completion of public comment periods and board approval, the 2023 PPRBC will be submitted to each jurisdiction for approval. Once approved, we will formally adopt the 2023 PPRBC.
Public comment process
To participate in public comment, click the link below. You will be taken to the project landing page to select the section of the 2023 PPRBC you wish to view and comment on, or select the appropriate project to submit a new amendment recommendation.
All comments will be reviewed by RBD staff. RBD reserves the right to contact you if additional clarification is needed.
Code Development Schedule
Topic |
Start Date |
End Date |
Status |
First Round Public Comment |
July 1, 2022
|
August 31, 2022
|
In Progress
|
Code Reconciliation and Board of Review work session |
September 1, 2022
|
September 30, 2022
|
TBD
|
Second Round Public Comment |
October 1, 2022
|
October 31, 2022
|
TBD
|
Code reconciliation of final 2023 PPRBC Draft |
November 1, 2022
|
November 15, 2022
|
TBD
|
Board of Review/Building Commission work sessions on final 2023 PPRBC Draft |
November 16, 2022
|
December 31, 2022
|
TBD
|
Board of Review approval |
December, 2022
|
December, 2022
|
TBD
|
Building Commission approval |
December, 2022
|
December, 2022
|
TBD
|
Jurisdictional approval |
TBD, 2023
|
TBD, 2023
|
TBD
|
Code Adoption Schedule
Topic |
Start Date |
End Date |
Status |
Pending schedule above |
TBD, 2023
|
TBD, 2023
|
TBD
|